Parking Lot Rehabilitation - AFLC
Please be advised that parking lot rehabilitation work is taking place at the Aurora Family Leisure Complex (AFLC), located at 135 Industrial Parkway North. Work is expected to continue until September 9, 2026, weather and site conditions permitting.
The work includes:
- Removal and replacement of sections of curb and sidewalk
- Restoration of disturbed areas
- Milling/grinding of the existing parking lot surface
- Adjustment of catch basins
- Placement of a new asphalt surface
- Line painting and final site cleanup
The current construction schedule is as follows:
|
Activity |
Scheduled Dates |
|
Curb removal and replacement |
August 4–12 |
|
Sidewalk removal and replacement |
August 13–18 |
|
Restoration |
August 19 |
|
Parking lot milling/grinding |
August 20–24 |
|
Catch basin adjustments |
August 25–26 |
|
Surface asphalt paving |
August 27–September 4 |
|
Line painting |
September 7–8 |
|
Cleanup and demobilization |
September 9 |
Access and Parking
The AFLC will remain accessible during construction; however, users should expect temporary changes to parking, vehicle circulation and pedestrian routes as work progresses through the site. Portions of the parking lot may be temporarily unavailable to accommodate construction activities.
Traffic control measures and signage will be in place to direct motorists and pedestrians around active work areas. Please use caution when travelling through the site and follow all posted signage and directions from construction personnel.
The Town will work with the contractor to minimize disruptions to facility users, Aurora Youth Soccer Club activities and surrounding residents wherever possible.
Please note that the schedule is subject to change due to weather, unforeseen site conditions or construction requirements.
We appreciate everyone’s patience and cooperation while these improvements are completed.