Reconstruction of Whispering Pine Trail, Orchard Heights Boulevard and Harmon Avenue

Message

​Contract#: 2018-23-PDS-ENG

Project Administrator: Norman Whitley 905-727-3123 x4376 nwhitley@aurora.ca

Project Engineer: Dan Vink 905-727-3123 x4380 dvink@aurora.ca

  • Harmon Avenue (from McLeod Drive to Gilbank Drive) - 0.64 lane kilometres of mill and 50mm overlay. 1 oil/grit separator to be installed.
  • Orchard Heights Boulevard (from Bathurst Street to Hill Drive W) - 2.44 lane kilometres of mill and 50mm overlay. 1 oil/grit separator to be installed.
  • Whispering Pine Trail (from Aurora Heights Drive to Orchard Heights Boulevard) - 0.93 lane kilometres of mill and 50mm overlay. 1 oil/grit separator to be installed.
  • Please visit our Summer Construction Projects Webpage at https://bit.ly/2D8VWsK for more information regarding this project.

Estimated Completion Date: August 2018